Permits in Denver go through the City and County of Denver's Community Planning and Development department (CPD), and Denver amends the international codes more than most cities. Whether it's an ADU in the Highlands, a big remodel in Wash Park or a tenant improvement in RiNo, a set that misses a local requirement can sit in review for a long time.

This guide is for Denver contractors, owners, architects and engineering firms putting a set together for CPD.

1. Denver's codes and amendments

Denver builds on the International Building Code and International Residential Code, with its own amendments in the Denver Building and Fire Code. Check which edition is in force on the day you submit, and cite it on the cover sheet.

The local items that most often affect the drawings:

Energy code and electrification

Denver has one of the more demanding municipal energy codes in the country.

  • Envelope: Denver is in climate zone 5B, and wall assemblies often need continuous insulation to meet the requirements. Show the full assembly in the wall sections.
  • Electrification: new homes and larger additions have to be ready for all-electric equipment: panel capacity and circuits for heat pumps, heat pump water heaters and EV charging. Show that capacity on the electrical sheets.
  • Windows: schedule the U-factor and SHGC of every window and door so the reviewer can check them.

Green Buildings Ordinance

Larger buildings (25,000 sq ft and up) fall under Denver's Green Buildings Ordinance, which asks for things like cool roofs, green roofs or on-site renewables. The drawings need to show which path the project takes.

2. Front Range structural criteria

The structural sheets, drawn from the engineer of record's design, need to reflect Denver's conditions:

ItemDenverOn the drawings
Frost depth36 inches below gradeFooting and pier details
Ground snow loadper the Denver amendments (commonly 30 psf)Drift at valleys, parapets and high walls
Windper the Denver amendmentsHold-downs, shear walls and uplift connections
SeismicSeismic Design Category BGeneral structural notes
Expansive soilscommon in Front Range claysVoid forms under grade beams, slab isolation

Where there's a soils report, the foundation details should follow its recommendations. Expansive soil details are an easy place for comments if they're missing.

3. A Denver submittal checklist

Denver takes applications online through its e-permits system. A typical set is organized like this:

Cover sheet and zoning

Zoning is its own review in Denver, and it is worth checking before the design is drawn: our guide to the Denver Zoning Code for houses explains zone districts, the bulk plane, block-sensing setbacks and coverage.

  • Parcel: the assessor's schedule number and legal description.
  • Zone district: for example U-SU-C, E-TU-B or C-RX-5.
  • Zoning table:
    • Lot coverage, allowed and proposed.
    • Bulk plane compliance: the sloped plane from the side lot lines that the building has to stay inside.
    • Setbacks, including eaves and projections.
    • Heights of the main and accessory buildings.
  • Codes: the code editions and Denver amendments that apply.

Architectural sheets

  • Site plan: property lines, right-of-way, curb cuts, utilities and grades.
  • Existing and demolition plans: clear line weights for what stays and what goes.
  • Floor plans: room names and areas, egress windows (5.7 sq ft clear opening), smoke and CO alarms.
  • Elevations: existing and finished grade, plate heights, the bulk plane drawn on, and finishes.
  • Sections and details: fire-rated walls within 5 feet of a lot line (IRC R302).

Structural sheets

  • A foundation plan coordinated with the underground plumbing.
  • Floor and roof framing with beam sizes and connections.
  • Schedules for shear walls, nailing and anchor bolts, from the engineer's calculations.

MEP sheets

  • Mechanical: equipment schedule, duct layout, outdoor unit clearances and combustion air.
  • Electrical: one-line diagram, panel schedule and load calculation, AFCI and GFCI notes, lighting.
  • Plumbing: drain and vent riser, fixture unit counts and cleanouts.

4. Getting the drafting done

Denver architects, engineering firms and contractors often have more work than drafting hours. The principals are on site and in meetings, and the engineer's markups need turning into clean sheets.

That's the work we do:

  • 3 to 5 business days for a typical residential set once the design or the engineer's markups are confirmed.
  • A fixed quote based on the sheets needed, from $499, with no hourly overruns.
  • Your software and standards: AutoCAD, Revit or Chief Architect, with your layers, text styles and title block.
  • Two rounds of revisions included. When CPD sends comments, we update the set and it goes back to the engineer of record for sign-off.

Send your Denver project for a quote.

Topic Cluster · Tools & Drafting Services

Related calculators & drafting services

Check your numbers with the free calculators, or have the sheets drawn by the studio.

Contractor & Builder Resource

Permit and plan-check notes, in your inbox

For contractors, builders and remodelers: plan-check checklists, code changes worth knowing and drafting tips from the studio. About once a month.

I am a:
No spam · About once a month · One-click unsubscribe